Acceptance Testing Requirements
• Make sure all requirements of the permit have been met prior to calling for an Acceptance Test.
• All system and related components shall be FULLY TESTED and ready for Acceptance Testing.
• All required permits (fire department and city or county) shall be on site for the inspector's review.
• System failure may result in a $300.00 re-inspection fee.
Permitting
Plans shall include information based on the requirements of the currently adopted Fire Code, as amended, and the appropriate NFPA Standards.
Minimum documentation/submittal requirements shall follow:
> IFC Ch. 1
> NFPA 72 Ch. 7 (Fire Alarm)
> NFPA 13 Ch. 23 (Sprinkler)
• All plans shall be drawn to scale and submitted on a minimum size of 18" by 24".
• Data sheets are required for all equipment
• Fire Suppression and Fire Detection Systems plans shall require at least a NICET III or a Professional Engineer stamp from an engineer who is trained in the design of the particular system being installed.
• Standpipe-1 1/2" couplings shall be iron pipe thread. 2 1/2" couplings shall be National Standard thread.
• All standpipes should have a 2 1/2" outlet with an 1 1/2" reducer.
City or County permits may be required for work being done with regard to smoke detection or automatic sprinkler systems.
Life Safety Links
- Fees
- Construction & Building Services
-
Fire Alarms Sprinkler Permitting
Fire Alarm System Reduction or Removal Process
Fire Life Safety Site Plan Submittal
Construction Management Site Plan Requirements
- Construction Permit Applications
-
Access Control Permit Application
Carbon Dioxide System Permit Application
Fire Alarm Control Panel (Dialer) Permit Application
Fire Suppression Permit Application
Kitchen Hood Suppression System Permit Application
Medical Gas Install Permit Application
New Building/Core and Shell Permit Application
Photovoltaic Permit Application
Radio Amplification System Permit Application
- Code Compliance
- Community Education & Risk Reduction
- Burn Restrictions and BBQ Regulations
-